Borana Weaves Limited (BORANA)
Capacity addition
Capacity addition at Unit 4 approved by Board on Nov 2, 2026
- Existing capacity: 1,212 Water Jet Looms, 349.05 mn metres annual production
- Expansion: 384 looms in two phases of 192 each; total capacity post-expansion 1,596 looms, 459.64 mn metres
- Phase 1 completion by Dec 2026; Phase 2 by Mar 2027
- Investment Rs 49.92 Cr funded by internal accruals and debt
- Aim to broaden product portfolio, attract high-value buyers, and improve cost efficiency
Source: Original filing PDF
—
view on exchange portal
⚡ You're reading this after the fact — subscribers got it instantly
ISA
Indian Stock Alerts
BOT
🚨 BORANA — Quarterly Results
Revenue: ₹2,35,800 Cr (+12% YoY)
PAT: ₹19,200 Cr (+17% YoY)
EBITDA margin: 16.8%
Board declared ₹10/share dividend. Jio adds 8M subs.
📎 bseindia.com/xml-data/...
🎧 Audio summary ready
✓✓ 6:47 PM
Instant audio summaries2-min AI concall recap delivered with every earnings alert
20-quarter financialsRevenue, PAT, EBITDA, margins — auto-extracted from filings
Forensic red-flag screenAudit, governance, accruals & RPT flags scored automatically
Instant Telegram alertsResults, board meetings, insider trades — within minutes
Add BORANA to your watchlist — all of this, automated.
Sign in with Google14-day Pro trial · No credit card · Cancel anytime
More on Borana Weaves Limited
Important.
The summary above is generated automatically from Borana Weaves Limited's own
public regulatory filing under SEBI LODR. Indian Stock Alerts is
not a SEBI-registered Research Analyst or Investment Adviser.
This page is informational, not investment advice, a recommendation to buy
or sell any security, or any opinion about the company's business, governance
or financial health. Always read the original filing before acting and consult
a registered adviser for investment decisions.