Update on delay in commissioning timelines of 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat
- One WTG location with 7.65 MW solar component expected by Sep 30, 2026
- Remaining two WTG locations expected by end Oct 2026
- Delay due to high wind speeds, heavy monsoon, and transmission line shutdown delays
- Company to keep stakeholders informed of developments
Source: Original filing PDF
—
view on exchange portal
⚡ You're reading this after the fact — subscribers got it instantly
ISA
Indian Stock Alerts
BOT
🚨 BORANA — Quarterly Results
Revenue: ₹2,35,800 Cr (+12% YoY)
PAT: ₹19,200 Cr (+17% YoY)
EBITDA margin: 16.8%
Board declared ₹10/share dividend. Jio adds 8M subs.
📎 bseindia.com/xml-data/...
🎧 Audio summary ready
✓✓ 6:47 PM
Instant audio summaries2-min AI concall recap delivered with every earnings alert
20-quarter financialsRevenue, PAT, EBITDA, margins — auto-extracted from filings
Forensic red-flag screenAudit, governance, accruals & RPT flags scored automatically
Instant Telegram alertsResults, board meetings, insider trades — within minutes
Add BORANA to your watchlist — all of this, automated.
Sign in with Google14-day Pro trial · No credit card · Cancel anytime
More on Borana Weaves Limited
Important.
The summary above is generated automatically from Borana Weaves Limited's own
public regulatory filing under SEBI LODR. Indian Stock Alerts is
not a SEBI-registered Research Analyst or Investment Adviser.
This page is informational, not investment advice, a recommendation to buy
or sell any security, or any opinion about the company's business, governance
or financial health. Always read the original filing before acting and consult
a registered adviser for investment decisions.